Reconstruction of 110/35/10 kV transformer substation N.Akmene. End user Lesto, UAB

Reconstruction of 35/10 kV part in 110/35/10 kV substation N.Akmene. All old equipment was changed by new one, 7 new substations were integrated in SCADA system. Main contractor Siemens Osakeyhtio Lithuania, UAB chooses Aedilis, UAB to complete all commissioning task for this substation;

RTU:
Aedilis, UAB team assembled a cubicle of RTU with Siemens AK 1703 ACP, TM1703ACP controllers in this project. Did a commissioning of RTU and detailed design;

Telecommunications:
Aedilis, UAB supplied all radio equipment for telecommunications and did a detailed design and commissioning;

Relay protection and automation:
Aedilis, UAB team did commissioning of all relays;

Automated system for power resources monitoring and accounting:
Our team assembled a cubicle for automated system for power resources monitoring and accounting with MDC1.01 controller and did a commissioning works;

Dispatcher panel:
Our team designed, assembled and commissioned a dispatcher panel for control room;

 

 